For over 50 years Biach has been a provider of custom designed bolt and stud tensioning systems to diverse industries world wide.
 

Case Histories: Power Generation

Biach engineers respond to one of a kind problems encountered by customers in many diverse industries.

Foreign Object Surveillance & Retrieval (FOSAR)- Knowledge & Procedure Documentation
 
 
 
Customer: Arizona Public Service - Foreign Object Surveillance & Retrieval (FOSAR)

Problem:  Customer was faceing the loss of undocumented worker knowledge, experience and lessons learned by the Maintenance and Fuels groups surrounding the use of the FOSAR system at Palo Verde station.

Solution:  Biach  conducted
on-site data collection and interviews with SME’s (Subject Matter Experts) from the Maintenance, Radiation Protection and the Fuels groups.

We analyzed and organized the data using a structured format to provide both new and experienced crews with easily accessible and understandable” just-in-time” and refresher training, as well as pre-job briefings.

Biach produced both web-suitable electronic versions as well as hard-copy bound versions for delivery and access at Palo Verde station.

 
 
 
 
Gas Turbine
 
     
 
Customer: Westinghouse

Problem:  Customer was having Problems balancing turbine rotors. During high speed  testing, rotor bolts would shift outward due to centrifugal force. This was due to the difference in diameter between the bolt and the clearance hole in the turbine discs, which was  necessary. To overcome this it would be necessary to force the rotor bolts outward during  tensioning..

Solution:  Biach  provided a system consisting of dual tensioners mounted on a rigid frame.  We included a cam actuated device to hold the rotor bolts and nuts against the outer portion of the disc hole during  tensioning.
 
     
 
Wind Turbine
 
     
 
Customer: General Electric

Problem:  150 foot diameter blades on windmill caused severe vibrations on couplings joining blade shaft to turbine generator and connecting shafts to gearing.

Solution:  Biach provided special high capacity tensioners having heavy duty gearing to properly seat the high torque lock nuts being used.
 
 
 
 
RPV Stud Tensioning
 
     
 

Customer: Nuclear Generation Stations thoughout the United States

Problem: RPV stud tensioning with manual tensioners took 2-3 shifts to complete.

Solution: Today’s version of the QD-H tensioner and EPN pump allow tensioning in less than one hour, saving critical path replacement power costs, reducing dose to workers and getting plants back on line to produce power sooner.

 
     
 
Reactor to Containment Anchoring
 
     
 
Customer: GETSCO Leibstadt Nuclear Plant

Problem:
 General Electric wanted a vendor to build  equipment for anchor bolts; do the actual tensioning, run tests, verify loads, provide QA data, provide manuals, obtain approvals and release a final report.

Solution: Biachs personnel designed special tensioning equipment and successfully handled the entire contract including the approval of the Swiss  government.
 
     
 
Reactor Internals - Bolting
 
     
 
Customer: General Electric

Problem:  Customer had two major Problems.  One was large tab washers under the nuts; the second was the lack of access for their personnel inside the reactor. Elongation readings had to be taken during assembly and at periodic intervals during the life of the reactor.  Personnel had to operate the equipment 25 feet above the joints from outside the reactor.

Solution:  Biach built compact, two piece tensioners having special bridge type bases, flexible shafts 25 feet long for engaging puller bars with the studs and to rotate the nuts.  A built-in electronic sensing device  indicated stud elongation.  All equipment was operated remotely.
 
     
Heat Exchangers
     
 
Customer: Manning & Lewis

Problem: Customer had difficulty tightening nuts and experienced repeated leaks. Current  methods involved torque and impact wrenches. Project took all day and frequently they had to shut down and tighten again.

Solution: Biach technicians, using our "C" style tensioners, assisted our customer and secured the cover in a little over two hours. They were amazed at the ease and speed of  tensioning. Additionally, there were no  leaks.  They were now able to decrease  their assembly time of heat exchangers.
 
     
 
Circulating And Reactor Coolant Pumps
 
     
 
Customer: Byron Jackson BWIP International

Problem: Manufacturer was having problems assembling large tapered pump shafts to  coupling flanges. Conventional methods  of assembling these components utilized sledge hammers, brute force and hope.

Solution: Biach developed a special type of hydraulic jack which mounts on the coupling to facilitate assembly and disassembly of pump  shafts. Referred to as the "push-pull" hydraulic jack, the equipment consists of a common hydraulic jack  that can be pressurized in both directions. By simply reversing the puller bar, component's position and using dual pumping control levers on a special portable hydraulic pumping unit, the crew can easily use the same equipment for both  operations.
 
     
 
High Pressure Turbine - Nuclear Plant
 
     
 

Customer: Duke Power  McGuire Nuclear Plant

Problem: Customer asked Biach to design a tensioner to replace units supplied by another manufacturer (Diamond). Due to mechanical problems with those units, the tensioning activities were taking Duke crews in excess of 65 hours to complete. This equipment had been supplied with the turbine by Westinghouse Electric.

Duke wanted easier means of handling since working conditions  were difficult and hoist facilities limited. They also wanted a faster means of nut turning as the current tommy bar method took extensive time.

Additionally, they wanted the tensioner to address two different stud sizes: 3.5" and 2.5" diameters with residual loads of 50Kpsi and 45Kpsi, respectively.

Solution: Biach engineers addressed the problem with a  tensioner consisting of several components, which made lifting and transporting  easier since it could be done manually, by one man. Hoists were no longer required (each  component was kept under 100# and lifting handles were mounted on  each).

Result: Duke could now  perform the tensioning process quickly and easily, without requiring an overhead hoist and crane.  The Biach gearing  system provi
ded a more accurate and faster means of seating the nuts, thereby assuring them reliable performance.

 
 
 
 
Primary Manway Cover
 
 
 
 
Customer: Duke Power  McGuire Nuclear Plant

Problem:  This aluminum primary manway tensioning ring was designed to tension 16) 1-7/8” studs simultaneously.  Duke was using individual tensioners previously and experiencing excessive time and dose in the process of opening and closing the manway covers.

Solution:  Biach designed a tensioning system providing 100% tensioning, greatly reducing time and exposure cost.
 
 
 
 
Metal Rod Shearing
 
 
 
 
Customer: Allis Chalmers

Problem:  Customer was looking for a method to cut contaminated control rods. The radioactive rods had to be sheared under water.

Solution:  Biach provided a portable, hydraulically operated, remotely operated, 100 ton cut-off tool.
 
     
 
ICI - Flange Bolting
 
     
 
Customer: Baltimore Gas & Electric Calvert Cliffs

Problem:  Process was too slow and very costly using torque wrenches on critical path. Too much exposure for crews.

Solution:  Biach provided a  tensioning system to tighten 50% of the studs simultaneously. This greatly reduced the bolt-up time and saved customer substantial money and exposure.
 
     
 
Stop Valve Cover
 
 
 
 

Customer: General Electric

Problem:  Recently, General Electric requested Biach Industries, Inc. to design a stud tensioning system for  their stop valve covers. We considered  the following data:

  • Stud Diameter: 3-1/4", special tapered thread
  • Number of Studs:17
  • Required Residual  Load: 22,000 psi
  • Nut Design: Special, slotted
  • Special Heavy Washer Used: 5-3/8" x 3-1/2"


Solution:  We developed a special  tensioner to meet their requirements, Its design incorporates:

  • Spring Powered Piston  Return System â€" to provide quick piston retracting to start the next  stroke.
  • Bevel Gear Drive for Turning and Seating the Nut - fast, simple and accurate for even loading.
  • A unit with 252,000 lbs. capacity @ 7975 psi pump pressure.
  • Dual hydraulic ports to  allow inlet from either side.
  • A special tall base  assembly to fit over their unique nut and washer.
  • Substantial radial cut-outs to clear adjacent nuts and washers.
 
 
 
 
Vessel Head Bolt-up
 
     
 
Customer: Perfex

Problem:  Fabricator of pressure vessels was looking  for ways to save time and money in their manufacturing and for their customer's maintenance. They decided to standardize on one size stud and nut..

Solution: Biach developed a tensioner to handle their application. Perfex standardized the Biach tensioners,  bought them in quantities and shipped four with each vessel they manufactured which provided their customers with real "cost of ownership" benefits
.
 
 
Steam Generator Ringless Nozzle Seal
 
     
 

Customer: Westinghouse Electric

Problem: Customer needed to expand Ringless Nozzle Seal legs prior to seal insertion. Also  needed to exert 15,000 lb. axial load to cover after installation in the nozzle.

Solution: Biach designed  tensioners with 3" strokes, male puller bars, annular thread design and nut drive with reversible air motor control.

 
     
 
 

View page as PDF document.

For more information contact Rob Gregory robg@biach.com